If you select a Risk Register with multiple projects, you will have to select one to associate with a PPM NextGen project.
To import risks with multiple projects from PPM NextGen, complete the following:
-
Select the S3 // Risk tab.
-
In the Import / Publish group, click
PPM NextGen.
-
On the Connect PPM NextGen Project dialog, navigate to the
Select a Project field.
-
Select a project from the dropdown menu.
-
Navigate to the
Select a PPM NextGen Project field.
-
Select a PPM NextGen project.
-
Click
Link.
-
In the Please Select Risks To Import dialog, select or clear the corresponding checkboxes of the risks you want to import.
-
Click
OK.
After you have successfully linked a PPM NextGen project to an Acumen project, an "E" icon will display next to the project name in the Risk Register tree.